Turbine Setting Discussion

The Rock Creek Diversion Dam Project

Version Dated : 12/16/2004

 

Turbine setting:

 

The drawing titled "Turbine Setting" (Drawing # RC-T-3) is provided as a discussion sheet for turbine setting design.  Please refer to other drawings on this site and other drawings for a complete understanding of the site.  This drawing is scaled for printing at 11 by 14 inches.

 

 

Equipment Access:

 

The dam is approximately 20 minute drive on state road 70 from motels/restaurants/hardware in the town of Quincy.  Rt. 70 leads to the flat top of the dam.  The site is about 2.5 hours North of Sacramento, or 1 hour East of Chico.  Equipment must be brought from the road over the bridge shown in photo "Bridge to dam's central pier.JPG".  Access to the dam top is level and directly off a main road.  Pieces too heavy to pass over the dam catwalks could be come by barged.  There is a crane on the front of the dam central pier.

 

 

The 5’ x 8’ Vertical Shaft

 

There is a 3 ton hoist shown in the photo titled "Hoist on dam top over 5 by 8 foot shaft.JPG" over a 5 foot by 8 foot shaft that drops all the way to the turbine floor.  The turbine pieces must be lowered in pieces approximately 99' down this 5' by 8' vertical shaft.  The shaft top is shown from in photo "Shaft Entrance on top of dam.jpg" using this hoist. The Dam operator in the photo is standing directly over a 99' drop under the cover plate.

 

 

The Existing 30 inch Feed Pipe

 

Part way down this shaft is the horizontal 30 inch pipe currently carrying the fish release water across the shaft for release as a jet onto the dam apron edge.  This pipe and a 6" pipe are removable to facilitate equipment passage.  The 30 inch pipe is shown crossing the vertical shaft in photo titled "30 inch_pipe_level through shaft.jpg". The drawing RC-T-3 shows an elevation of the wall in this photo on its far left. There is a removable thin metal floor under the pipe and a grill over it.  All of which are wrench removable.

 

 

The Turbine floor

 

This is the main gate floor at the level of the bonnets of the abandon main gates.  The screwjacks and motor actuators are in place but disconnected at the switchboard.  The turbine mounting floor is shown in photo "Turbine_floor.JPG".  It is in two areas one the 5 by 8 foot flat area at the bottom of the shaft and adjoining is a more spacious area just upstream (left) in the gate mechanism area.  The area where the turbine is expected to go is in the general area of the “-T-” in this drawing.  Working in this area will require the removal of the gate hoisting equipment ( See Photos "handwheel_gate_open_main_gates.JPG" and "old hoisting motors.JPG".) and its supports that fills much of the middle of this area above the gate.  This is probably an acceptable design choice for a centrifugal turbine design of the mixed flow or Francis type.

 

In the lower right of the"Turbine Setting" drawing is a suggested bifurcation of the 30 inch pipe that will bring the water directly into the turbine floor area.  Other methods of bring water down would be a sharp bend into a vertical column following the existing shaft.  A vertical turbine/pump would work this way.  This type of turbine would be limited by cavitation, however, there is nothing to preclude lowering the runner base down in a new hole to close to tailwater level.  There is possibly more head available here than needed, so the draft tube may not need to recover much of the velocity head.  This will allow a higher setting of a runner.

 

The setting problem is to install the largest turbine/generator possible while removing as little concrete as is reasonable.  The equipment choice is to minimize installation, operation, and maintenance costs.

 

The reservoir/tail water head has a very small variation as this river is controlled for hydropower, however, the 30" pipe imposes a severe flow/pressure constraint.  To estimate the losses, one would assume 6" head loss through the trash rack (not shown on the setting sketch), a partly rounded corner on the entrance to the pipe, and 5 year old steel 30" nominal steel pipe with an assumed I.D. of 28.75 inches.  Currently, PG&E estimates that the maximum flow through the existing conduit is about 150 cfs as the pipe vents out to into the middle of the spillway at an elevation of 2152.75 (PG&E datum).  The calculations shown in the power analysis spreadsheet show a slightly higher maximum flow.